What the Dockets Say About October

Four addresses in front of HARC, Shandoka and Carhenge inching through review, a Mountain Village board that skips the month, and a film festival that fills the theaters just as the first snow hits the ridgelines.

UltraBuildersOctober 7, 20265 min read
The short version

Telluride's Historic and Architectural Review Commission has four addresses on its October 21 docket and the Planning & Zoning Commission has three on October 22, including the town's Shandoka housing project. Mountain Village's Design Review Board does not meet again until November 5. Town Council holds a special budget session on October 13. And the 17th Telluride Horror Show runs October 16 to 18, which is the last weekend of the year you will find a parking spot on Colorado Avenue by accident.

October is the month the valley exhales. The festival tents are down, the aspens have done their thing, and anyone building a house is doing math about how many dry days are left. It is also, quietly, one of the busiest months at Town Hall, because everything that wants to break ground in spring has to get through review now.

Here is what we are watching.

Telluride: HARC on the 21st, P&Z on the 22nd

If you own or are buying anything inside the Telluride town limits, the Historic and Architectural Review Commission is the board that decides what the outside of your house can look like. It issues a Certificate of Appropriateness before a permit can be pulled for building, demolishing, moving, adding to, or altering any structure or sign in town. HARC also keeps the inventory of historically and architecturally significant buildings, which is the list you want to check before you fall in love with a Victorian on the north side and start sketching a second storey.

The October 21 docket, as posted on the town’s public-notice page:

  • 214 S. Fir — back for another look. This one has been on the HARC calendar since December 2025 and has been continued twice, which tells you something about how much goes into a single facade in the historic district.
  • 448 Tomboy and 785 Primrose — new to the docket this month.
  • Shandoka, preliminary large-scale review — the Shandoka housing project, continued from August. The same project goes to the Planning & Zoning Commission the next day for its preliminary PUD.

On October 22, P&Z also takes up 238 N. Pine, a minor subdivision that has been continued since May, and 222 W. San Juan. A separate item for 510 W. Columbia is set for November 2.

Two things worth knowing if you have never sat through one of these meetings. First, “continued from” is not a bad sign; it usually means the applicant and staff are still trading drawings, and the board would rather see it right than see it fast. Second, HARC usually meets at Rebekah Hall, and the agendas and packets are posted on the town’s meeting portal a few days ahead. The packets are long, but the staff memo at the front of each item is the part worth reading: it tells you what staff is recommending and why, which is most of the outcome.

Carhenge, slowly

The town’s bigger housing story is the Carhenge lot, the surface parking area at the southwest end of town. The town’s planning team and its consultants have spent 2025 and 2026 turning it into a concept for a mixed-use neighborhood: community housing throughout, ground-floor community or commercial space, public open space, and the parking moved underground. Story poles went up in July so people could see the massing from the street, HARC held a public hearing on July 15, and the preliminary large-scale review was continued through August to September 30.

The town says Phase 3 is now underway, which means turning the preferred concept into an actual development proposal and starting formal land-use review: a subdivision application, a PUD, and a Large Scale Activity review, each with its own public hearing. No fall dates are posted yet. When they are, we will say so here.

Why a builder cares: a neighborhood of community housing at the edge of town would change the subcontractor labor picture for everyone, in a good way. The people who frame, plumb, and wire houses here mostly commute from Norwood, Ridgway, and Montrose. Housing in town is the single thing that would shorten every build schedule in the valley.

Mountain Village: no October meeting

Mountain Village runs design review through its Design Review Board, seven appointed members plus two alternates, chaired by Banks Brown. The DRB meets the first Thursday of most months at 10 a.m. in Town Hall. October is one of the months it skips: the next meeting is Thursday, November 5, at 10 a.m., followed by December 3.

If you are planning a Mountain Village project for spring, that November date is the one that matters. Miss it and you are into December, and December in the Village is a month when nobody wants to talk about anything but snow. Applications and questions go to planning@mtnvillage.org.

Town Hall, otherwise

  • Tuesday, October 13 — a special Town Council meeting on the budget. Budget season is when things like building-department staffing and plan-review timelines get decided, so it is more relevant to construction than it sounds.
  • Thursday, October 8 — San Miguel Authority for Regional Transportation (SMART), the regional transit authority, which matters to anyone whose crew rides the bus up from Norwood or Montrose.
  • Wednesday, October 21 — Parks & Recreation Commission, the same day as HARC.

The town’s year-long Comprehensive Plan update, which kicked off in June 2025 and was slated to wrap this summer, will set the land-use framework the next decade of projects gets reviewed under. We will cover where it landed in a coming note.

And then the Horror Show

The Telluride Horror Show returns for its 17th edition October 16 to 18: feature and short films, horror, suspense, dark comedy and the rest, many getting one of their first U.S. showings. It is the festival that fits this town best in October, when the light goes early and the theaters are warm. If you are coming up for it and you own a house here, it is also the last easy weekend to walk the property with your builder before the ground freezes.

What October means on a job site

A few things we tell every owner this time of year, none of them new:

  • Concrete has a calendar. Foundations poured now need protection from the first hard freezes. Anything that cannot be poured and cured by late October usually waits for spring, which is why so many projects race to get footings in now.
  • Dry-in before snow. Roof, windows, and weather barrier on before the storms stack up means an interior season of work. Miss it and you are shoveling the second floor.
  • Review timelines are the real schedule. A HARC continuance or a skipped DRB month moves your start date more than any weather does. The projects that break ground in May are the ones that were in front of a board in October.

That is the first note. Fridays from here on. If something in this one applies to a house you own or a lot you are considering, the office number is on every page of this site, and the people who answer it have sat through more of these meetings than they would like to admit.